NTPC’s Tapovan Vishnugad Hydroelectric  project achieves Head Race Tunnel breakthrough

NTPC Tapovan Vishnugad Hydroelectric Project Head Race Tunnel breakthrough

DEHRADOON. NTPC’s 520 MW Tapovan Vishnugad Hydroelectric Project said it has achieved a significant construction milestone with the successful breakthrough of the Head Race Tunnel (HRT). The officials said that this achievement was achieved through the precise breakthrough of the tunnels being constructed in Phase-02 and Phase-03, thereby successfully connecting the tunnels being constructed on both sides.

Sharing further details, they said that this breakthrough involved excavating 1,748 meters of tunnel from Phase 02 and 981 meters from Phase 03. With this success, 9.7 kilometres of excavation has been completed so far in the 12.1 kilometre long head race tunnel, which is about 80 per cent of the total excavation, they further said.

They claimed that braving the extremely challenging geological conditions, hard rock formations and complex underground construction conditions of the Himalayan region, the engineers and workforce, associated with the project, had demonstrated technical expertise, determination and commitment to safety and quality.

Related posts

Govt appoints Siddhartha Mohanty as LIC chairperson

Newsmantra

World Quality Week observation commences at SAIL, Rourkela Steel Plant

Newsmantra

ONGC Secures Triple Honors at 12th Governance Now PSU Awards

Newsmantra

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More